2 The procedure for determining the base price of design work
3 Basic prices for the development of design and working documentation
Table No. 1. City linear engineering communication networks
Table No. 2. External lighting of streets, highways, driveways, squares, parks, squares, boulevards, residential courtyard areas, cemeteries, areas of schools, kindergartens, nurseries, clinics and hospitals
Table No. 3. Certain types of outdoor lighting work
Table No. 4. City water supply
Table No. 5. External sewerage networks
Table No. 6. Structural components on city sewerage pipelines
Table No. 7. Separate units of rainwater drainage pipelines designed outside the complex
Table No. 8. Urban reservoirs
Table No. 9. Heat networks
Table No. 10. Pumping stations for pumping drainage water
Table No. 11. Boosters pumping stations
Table No. 12. Control and maintenance units for electrified valves
Table No. 13. Battery installations
Table No. 14. Central heating point
Table No. 15. Boiler rooms
Table No. 16. Diesel power plants
Table No. 17. Quarterly, inter-quarter, street cable electrical networks
Table No. 18. Overhead power lines with voltage up to 20 kV
Table No. 19. Overhead power lines with a voltage of 35 kV
Table No. 20. Overhead power lines with voltage 110 - 750 kV
Table No. 21. Transitions of overhead power lines 35 - 750 kV
Table No. 22. Special work on the design of power transmission lines 35 - 750 kV
Table No. 23. Electrical calculations for power lines with voltage 220 - 750 kV
Table No. 24. Special electrical calculations for power lines 35 - 750 kV
Table No. 25. Electrical substations AC 35 - 750 kV
Table No. 26. Additional technical specifications buildings and structures of substations, prices for the design of which are given in table No. 25
Table No. 27. Buildings and structures of AC electrical substations
Table No. 28. Technical reconstruction of secondary connections of existing switchgears (RU)
Table No. 29. Secondary connections of emergency and system automation devices (PA), automated systems (AS), signal reception and transmission (PI)
Table No. 30. Relay protection and linear automation of electrical networks 35 - 750 kV
Table No. 31. Calculations of short circuit currents in networks with voltages of 35 - 750 kV
Table No. 32. Emergency automation
Table No. 33. Calculations of electrical modes and stability in networks with voltages up to 750 kV inclusive
Table No. 34. Dispatch control and telemechanization of energy facilities of power systems
Table No. 35. High-frequency channels along power lines
Table No. 36. Certain types of work for overhead lines with voltage up to 20 kV
Table No. 37. Transformer substations voltage 6-20/0.4-10 kV, distribution and sectioning points with voltage 6 - 20 kV
Table No. 38. Relay protection of electrical networks with voltage up to 20 kV
Table No. 39. Linear automation of electrical networks with voltage up to 20 kV
Table No. 40. Calculation of short-circuit currents in electrical networks with voltages of 3 - 20 kV
Table No. 41. Electrical networks voltage up to 20 kV
Table No. 42. Underground communication tunnels
Table No. 43. Units, cameras and control rooms for servicing underground communication tunnels
Table No. 44. Recommended estimated relative cost of developing sections of design documentation for the construction of engineering structures and communications (as a percentage of the base price)
Table No. 45. Recommended estimated relative cost of developing working documentation for the construction of engineering structures and communications (as a percentage of the base price)
Table No. 46. Recommended estimated relative cost of developing sections of design documentation for the construction of linear facilities (as a percentage of the base price)
Table No. 47. Recommended estimated relative cost of developing working documentation for the construction of linear facilities (as a percentage of the base price)
Table No. 48. Recommended estimated relative cost of developing sections of design documentation for the construction of a complex of boiler houses and a central heating point (as a percentage of the base price)
Table No. 49. Recommended estimated relative cost of developing working documentation for the construction of a complex of boiler houses and a central heating point (as a percentage of the base price)
Table No. 50. List of abbreviations used in the Directory
1.1. State estimate standard "Directory base prices on design work in construction, "Utility engineering networks and structures" (hereinafter referred to as the Directory) is intended to determine the cost of developing design and working documentation for the construction of buildings, engineering structures and communications (water supply and sewerage networks, heat and power supply structures, linear engineering communication networks, external electric lighting).
1.2. When using this Directory, you should be guided by the Guidelines for the use of directories of basic prices for design work in construction, approved by the Order of the Ministry of Regional Development Russian Federation dated December 29, 2009 N 620 “On approval Guidelines on the use of reference books of basic prices for design work in construction" (registered by the Ministry of Justice of the Russian Federation on March 23, 2010, registration N 16686, Bulletin of regulatory acts of federal executive authorities, 2010, N 16) (hereinafter referred to as the Guidelines).
1.4. Basic prices in the Directory are established for the development of design and working documentation depending on the natural indicators of design objects: length, power, productivity and others, or for the object as a whole.
1.5. The distribution of the base price for the development of design and working documentation can be determined in accordance with paragraph 1.4 of the Methodological Instructions, while Chapters 2.3, 2.4, 2.7 and 2.8 of this Handbook provide updated regulations for the specified ratio, taking into account the specifics of the design of utility networks and structures.
1.7.7. Design of special production methods construction work(water reduction for the construction period, chemical consolidation and freezing of soils, hydromechanization, sheet piling of pits and trenches and others);
The cost of developing the “Industrial Safety” section, if it is developed by decision of the state customer, is determined in the amount of up to 6% of the cost of developing design documentation for those structures in respect of which this section is being developed;
1.9. The base prices of this Handbook provide for design based on geodetic plans on a scale of 1:500. When designing according to geodetic plans at a scale of 1:200, a pricing coefficient of up to 1.15 is applied to prices.
1.10. When designing facilities in cities with a population of 500 thousand to 1 million people, a pricing coefficient of up to 1.1 can be applied to prices; with a population of more than 1 million people - coefficient up to 1.2; for the cities of Moscow and St. Petersburg - a coefficient of up to 1.3, and when designing utility networks and structures in areas of historical value (historical part of the city), the price for design can be determined with a pricing coefficient of up to 1.4.
1.12. When metro lines and structures intersect, a coefficient of up to 1.2 can be applied to the design prices for utility networks and structures located in their area, taking into account complicating design factors.
If it is necessary to develop engineering support schemes (indicated in the design assignment), their cost can be determined at the prices of this Directory using a reduction factor of up to 0.2 to the cost of developing design documentation for the facility, which includes all structures on the construction site, including length newly designed communications serving the construction area.
1.14. In case of carrying out work to assess the impact of a capital construction project on environment(EIA) as part of the design documentation on behalf of the customer, their cost is determined in the amount of 4% of the total design cost.
1.15. The recommended approximate relative cost of developing sections of design and working documentation for the construction of engineering structures and communications (as a percentage of the base price) is given in tables No. 44 and No. 45 of this Handbook.
1.17. The recommended approximate relative cost of developing sections of design and working documentation for the construction of a complex of boiler houses and a central heating point (as a percentage of the base price) is given in Table No. 48 and No. 49 of this Handbook.
1.18. The base price for the development of design and working documentation for temporary structures (water supply, sewerage, etc.) necessary for the normal operation of existing facilities during the construction of the structure being designed is determined according to the prices of this Directory with a coefficient of up to 0.5.
1.19. The base price for the development of design and working documentation only for the dismantling of objects and structures (without further design of new objects and structures), if carried out under a separate design task, is determined at the prices of this Handbook for the design of sections, the development of which is necessary during dismantling, using coefficients: up to 0.35 - for the linear part and up to 0.2 - for on-site structures, taking into account the ratio of the labor intensity of design work for an object under conditions of new construction and the development of documentation for the dismantling of a similar object.
1 Basic provisions2 The procedure for determining the base price of design work
3 Basic prices for the development of design and working documentation
Table No. 1. City linear engineering communication networks
Table No. 2. External lighting of streets, highways, driveways, squares, parks, squares, boulevards, residential courtyard areas, cemeteries, areas of schools, kindergartens, nurseries, clinics and hospitals
Table No. 3. Certain types of outdoor lighting work
Table No. 4. City water supply
Table No. 5. External sewerage networks
Table No. 6. Structural components on city sewerage pipelines
Table No. 7. Separate units of rainwater drainage pipelines designed outside the complex
Table No. 8. Urban reservoirs
Table No. 9. Heat networks
Table No. 10. Pumping stations for pumping drainage water
Table No. 11. Booster pumping stations
Table No. 12. Control and maintenance units for electrified valves
Table No. 13. Battery installations
Table No. 14. Central heating point
Table No. 15. Boiler rooms
Table No. 16. Diesel power plants
Table No. 17. Quarterly, inter-quarter, street cable electrical networks
Table No. 18. Overhead power lines with voltage up to 20 kV
Table No. 19. Overhead power lines with a voltage of 35 kV
Table No. 20. Overhead power lines with voltage 110 - 750 kV
Table No. 21. Transitions of overhead power lines 35 - 750 kV
Table No. 22. Special work on the design of power transmission lines 35 - 750 kV
Table No. 23. Electrical calculations for power lines with voltage 220 - 750 kV
Table No. 24. Special electrical calculations for power lines 35 - 750 kV
Table No. 25. AC electrical substations 35 - 750 kV
Table No. 26. Additional technical characteristics of buildings and structures of substations, prices for the design of which are given in Table No. 25
Table No. 27. Buildings and structures of AC electrical substations
Table No. 28. Technical reconstruction of secondary connections of existing switchgears (RU)
Table No. 29. Secondary connections of emergency and system automation devices (PA), automated systems (AS), signal reception and transmission (PI)
Table No. 30. Relay protection and linear automation of electrical networks 35 - 750 kV
Table No. 31. Calculations of short circuit currents in networks with voltages of 35 - 750 kV
Table No. 32. Emergency automation
Table No. 33. Calculations of electrical modes and stability in networks with voltages up to 750 kV inclusive
Table No. 34. Dispatch control and telemechanization of energy facilities of power systems
Table No. 35. High-frequency channels along power lines
Table No. 36. Certain types of work for overhead lines with voltage up to 20 kV
Table No. 37. Transformer substations with voltage 6-20/0.4-10 kV, distribution and sectioning points with voltage 6-20 kV
Table No. 38. Relay protection of electrical networks with voltage up to 20 kV
Table No. 39. Linear automation of electrical networks with voltage up to 20 kV
Table No. 40. Calculation of short-circuit currents in electrical networks with voltages of 3 - 20 kV
Table No. 41. Electrical networks with voltage up to 20 kV
Table No. 42. Underground communication tunnels
Table No. 43. Units, cameras and control rooms for servicing underground communication tunnels
Table No. 44. Recommended estimated relative cost of developing sections of design documentation for the construction of engineering structures and communications (as a percentage of the base price)
Table No. 45. Recommended estimated relative cost of developing working documentation for the construction of engineering structures and communications (as a percentage of the base price)
Table No. 46. Recommended estimated relative cost of developing sections of design documentation for the construction of linear facilities (as a percentage of the base price)
Table No. 47. Recommended estimated relative cost of developing working documentation for the construction of linear facilities (as a percentage of the base price)
Table No. 48. Recommended estimated relative cost of developing sections of design documentation for the construction of a complex of boiler houses and a central heating point (as a percentage of the base price)
Table No. 49. Recommended estimated relative cost of developing working documentation for the construction of a complex of boiler houses and a central heating point (as a percentage of the base price)
Table No. 50. List of abbreviations used in the Directory